Assessment Year | 1988 |
---|---|
Principal Product | ADVERTISING DISPLAYS |
NAICS |
n/a
|
SIC | 3993: Signs and Advertising Specialties |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
n/a
|
Annual Production | 175,000
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $163,252 | 2,902,110 |
kWh
|
$0.056 |
Natural Gas | $98,088 | 25,314 |
MMBtu
|
$3.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,545 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,545 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $4,805 | $1,029 | - |
$4,805
-
MMBtu
|
|
02 | 2.7261: Install timers and/or thermostats | $4,469 | $3,650 | - |
$4,469
-
MMBtu
|
|
03 | 2.2136: Install / repair insulation on steam lines | $4,263 | $1,014 | - |
$4,263
-
MMBtu
|
|
04 | 2.2113: Repair or replace steam traps | $3,440 | $725 | - |
$3,440
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,980 | $550 |
$10,980
196,073
kWh
|
- | |
06 | 2.2135: Repair and eliminate steam leaks | $932 | $665 | - |
$932
-
MMBtu
|
|
07 | 2.4221: Install compressor air intakes in coolest locations | $656 | $885 |
$656
11,723
kWh
|
- | |
TOTAL RECOMMENDED | $29,545 | $8,518 |
$11,636
207,796
kWh
|
$17,909
-
MMBtu
|
||
TOTAL IMPLEMENTED | $29,545 | $8,518 |
$11,636
207,796
kWh
|
$17,909
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs