ITAC Assessment: TN0331
ITAC logo
ITAC Assessment: TN0331
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product ADVERTISING DISPLAYS
NAICS
n/a
SIC 3993: Signs and Advertising Specialties
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 175,000
pieces
Production Hrs. Annual 0
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $163,252 2,902,110
kWh
Natural Gas $98,088 25,314
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,545 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,545

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $4,805 $1,029 - $4,805
-
MMBtu
02 2.7261: Install timers and/or thermostats $4,469 $3,650 - $4,469
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $4,263 $1,014 - $4,263
-
MMBtu
04 2.2113: Repair or replace steam traps $3,440 $725 - $3,440
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,980 $550 $10,980
196,073
kWh
-
06 2.2135: Repair and eliminate steam leaks $932 $665 - $932
-
MMBtu
07 2.4221: Install compressor air intakes in coolest locations $656 $885 $656
11,723
kWh
-
TOTAL RECOMMENDED $29,545 $8,518 $11,636
207,796
kWh
$17,909
-
MMBtu
TOTAL IMPLEMENTED $29,545 $8,518 $11,636
207,796
kWh
$17,909
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs