| Assessment Year | 2013 |
|---|---|
| Principal Product | CCD Sensors |
| NAICS | 334413: Semiconductor and Related Device Manufacturing |
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
263,000
ft2
|
| Annual Production | 250,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,930,427 | 21,397,000 |
kWh
|
$0.090 |
| Electricity Fees | $255,426 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,281,892 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,811 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.821: Pay bills on time to avoid late fees | $6,610 | - | - | - | $6,610 | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $20,356 | $4,000 |
$(-14,770.0)
(-164,112)
kWh
|
- | $35,126 | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $4,244 | $2,033 |
$4,244
47,156
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $457 | $216 |
$87
963
kWh
|
- | $370 | |
| 05 | 2.2628: Utilize a less expensive cooling method | $882,762 | $552,244 |
$(-272,938.0)
(-3,032,640)
kWh
|
- | $1,155,700 | |
| 06 | 2.1392: Replace purchased steam with other energy source | $361,538 | $453,062 | - |
$(-713,405.0)
-
MMBtu
|
$1,074,943 | |
| 07 | 3.1161: Eliminate/reduce an operation | $2,724 | $5,760 |
$(-66.0)
(-732)
kWh
|
- | $2,790 | |
| 08 | 2.4321: Upgrade obsolete equipment | $3,201 | $8,460 |
$3,201
35,568
kWh
|
- | - | |
| TOTAL RECOMMENDED | $1,281,892 | $1,025,775 |
$(-280,242.0)
(-3,113,797)
kWh
|
$(-713,405.0)
-
MMBtu
|
$2,275,539 | ||
| TOTAL IMPLEMENTED | $9,811 | $8,460 |
$3,201
35,568
kWh
|
- | $6,610 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs