| Assessment Year | 1987 |
|---|---|
| Principal Product | PLASTIC FURNITURE |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 10,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $313,182 | 6,065,065 |
kWh
|
$0.052 |
| Natural Gas | $17,755 | 3,534 |
MMBtu
|
$5.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,189 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,619 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $10,943 | $650 |
$10,943
210,434
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $2,510 | $2,700 | - |
$2,510
-
MMBtu
|
|
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,630 | $12,000 |
$6,630
127,491
kWh
|
- | |
| 04 | 2.6232: Install set-back timers | $4,039 | - |
$4,039
77,667
kWh
|
- | |
| 05 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,637 | $2,680 |
$2,637
50,703
kWh
|
- | |
| 06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,707 | - |
$1,707
32,825
kWh
|
- | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,174 | - |
$1,174
22,567
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $549 | $94 |
$549
10,551
kWh
|
- | |
| TOTAL RECOMMENDED | $30,189 | $18,124 |
$27,679
532,238
kWh
|
$2,510
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,619 | $3,330 |
$17,619
338,804
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs