ITAC Assessment: TN0299
ITAC logo
ITAC Assessment: TN0299
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product FURNITURE SPRINGS
NAICS
n/a
SIC 2515: Mattresses, Foundations, and Convertible Beds
Sales Range $5
M
to 10
M
# of Employees 74
Plant Area
n/a
Annual Production 3,750,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,703 556,858
kWh
Natural Gas $51,114 9,988
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,739 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,175

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $1,498 $429 - $1,498
-
MMBtu
02 2.2414: Use waste heat from hot flue gases to preheat $1,301 $2,000 - $1,301
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,747 $165 $3,747
55,100
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $453 $1,192 - $453
-
MMBtu
05 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $1,674 $930 $1,674
24,619
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,555 $1,600 $1,555
22,860
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,335 $360 $1,335
19,637
kWh
-
08 2.6232: Install set-back timers $1,176 - $1,176
17,292
kWh
-
TOTAL RECOMMENDED $12,739 $6,676 $9,487
139,508
kWh
$3,252
-
MMBtu
TOTAL IMPLEMENTED $8,175 $3,786 $4,923
72,392
kWh
$3,252
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs