| Assessment Year | 1987 |
|---|---|
| Principal Product | FURNITURE SPRINGS |
| NAICS |
n/a
|
| SIC | 2515: Mattresses, Foundations, and Convertible Beds |
| Sales Range | $5 M to 10M |
| # of Employees | 74 |
| Plant Area |
n/a
|
| Annual Production | 3,750,000
pieces
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $37,703 | 556,858 |
kWh
|
$0.068 |
| Natural Gas | $51,114 | 9,988 |
MMBtu
|
$5.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,739 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,175 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $1,498 | $429 | - |
$1,498
-
MMBtu
|
|
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $1,301 | $2,000 | - |
$1,301
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,747 | $165 |
$3,747
55,100
kWh
|
- | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $453 | $1,192 | - |
$453
-
MMBtu
|
|
| 05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,674 | $930 |
$1,674
24,619
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,555 | $1,600 |
$1,555
22,860
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,335 | $360 |
$1,335
19,637
kWh
|
- | |
| 08 | 2.6232: Install set-back timers | $1,176 | - |
$1,176
17,292
kWh
|
- | |
| TOTAL RECOMMENDED | $12,739 | $6,676 |
$9,487
139,508
kWh
|
$3,252
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $8,175 | $3,786 |
$4,923
72,392
kWh
|
$3,252
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs