Assessment Year | 2007 |
---|---|
Principal Product | Aluminum beverage containers |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
330,000
ft2
|
Annual Production | 3,200,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,695,916 | 47,784,906 |
kWh
|
$0.035 |
Electricity Demand | $894,041 | 69,935 |
kW-mo/yr
|
$12.78 |
Electricity Fees | $1,566 | - |
|
- |
Natural Gas | $1,322,170 | 147,235 |
MMBtu
|
$8.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $141,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1113: Reduce combustion air flow to optimum | $77,320 | $140,620 |
$4,720
146,100
kWh
|
$2,720
-
kW-mo/yr
|
$69,880
-
MMBtu
|
- | |
02 | 2.1116: Improve combustion control capability | $37,380 | $112,000 | - | - |
$37,380
-
MMBtu
|
- | |
03 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $15,090 | $338,400 |
$46,010
1,423,100
kWh
|
$27,800
-
kW-mo/yr
|
$(-32,320.0)
-
MMBtu
|
$(-26,400.0) | |
04 | 2.4131: Size electric motors for peak operating efficiency | $8,960 | $14,520 |
$5,690
176,100
kWh
|
$3,270
-
kW-mo/yr
|
- | - | |
05 | 2.1213: Direct warmest air to combustion intake | $1,660 | $4,250 | - | - |
$1,660
-
MMBtu
|
- | |
06 | 2.9114: Use solar heat to make electricty | $1,310 | $11,000 |
$470
14,600
kWh
|
$840
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $141,720 | $620,790 |
$56,890
1,759,900
kWh
|
$34,630
-
kW-mo/yr
|
$76,600
-
MMBtu
|
$(-26,400.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs