Assessment Year | 1986 |
---|---|
Principal Product | SNACK FOODS |
NAICS |
n/a
|
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
n/a
|
Annual Production | 4,160,000
pieces
|
Production Hrs. Annual | 4,992
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,239 | 2,039,273 |
kWh
|
$0.049 |
Natural Gas | $325,839 | 75,044 |
MMBtu
|
$4.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,426 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,806 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,791 | - | - |
$6,291
-
MMBtu
|
$500 | |
02 | 2.2425: Use flue gases to heat process or service water | $5,418 | $17,075 | - |
$5,418
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $1,458 | $398 | - |
$1,458
-
MMBtu
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $1,277 | $750 | - |
$1,277
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,422 | $820 |
$1,422
29,015
kWh
|
- | - | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $288 | $1,000 | - |
$288
-
MMBtu
|
- | |
07 | 2.2122: Install / repair insulation on condensate lines | $159 | $35 | - |
$159
-
MMBtu
|
- | |
08 | 2.6232: Install set-back timers | $531 | - |
$531
10,844
kWh
|
- | - | |
09 | 2.2163: Use minimum steam operating pressure | $82 | - | - |
$82
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $17,426 | $20,078 |
$1,953
39,859
kWh
|
$14,973
-
MMBtu
|
$500 | ||
TOTAL IMPLEMENTED | $1,806 | $1,785 | - |
$1,806
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs