ITAC Assessment: MS0035
ITAC logo
ITAC Assessment: MS0035
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 260,000
ft2
Annual Production 212,500
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,005 2,452,521
kWh
Natural Gas $34,237 5,219
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,760 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,981

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7111: Reduce illumination to minimum necessary levels $817 $50 $817
23,740
kWh
-
02 2.3212: Optimize plant power factor $5,164 $2,130 $5,164
-
kWh
-
03 2.2428: Use flue gases in radiant heater for space heating, ovens, etc $11,921 $12,146 - $11,921
-
MMBtu
04 2.6214: Shut off pilots in standby equipment $678 $20 - $678
-
MMBtu
05 2.7261: Install timers and/or thermostats $2,158 $5,000 $2,158
70,926
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,824 $4,949 $2,824
41,618
kWh
-
07 2.2437: Recover waste heat from equipment $18,198 $32,850 - $18,198
-
MMBtu
TOTAL RECOMMENDED $41,760 $57,145 $10,963
136,284
kWh
$30,797
-
MMBtu
TOTAL IMPLEMENTED $5,981 $2,180 $5,981
23,740
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs