ITAC Assessment: TN0252
ITAC logo
ITAC Assessment: TN0252
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product FURNITURE
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 150,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,444 1,952,521
kWh
Natural Gas $2,810 444
MMBtu
LPG $22,497 2,819
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,614 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,394

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $6,105 $8,772 - $838
-
MMBtu
$5,267
-
MMBtu
02 2.4221: Install compressor air intakes in coolest locations $5,557 $180 $5,557
115,768
kWh
- -
03 2.7111: Reduce illumination to minimum necessary levels $3,545 - $3,545
73,857
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $732 $3,720 $732
15,240
kWh
- -
05 2.7111: Reduce illumination to minimum necessary levels $675 - $675
14,068
kWh
- -
TOTAL RECOMMENDED $16,614 $12,672 $10,509
218,933
kWh
$838
-
MMBtu
$5,267
-
MMBtu
TOTAL IMPLEMENTED $12,394 $12,672 $6,289
131,008
kWh
$838
-
MMBtu
$5,267
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs