ITAC Assessment: SJ0040
ITAC logo
ITAC Assessment: SJ0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Aircraft
NAICS 336411: Aircraft Manufacturing
SIC 3721: Aircraft
Sales Range $1
M
to 5
M
# of Employees 495
Plant Area 713,000
ft2
Annual Production 100
units
Production Hrs. Annual 3,744
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $789,202 4,372,866
kWh
Electricity Demand $643,420 18,169
kW-mo/yr
Natural Gas $105,507 5,275
MMBtu
TOTAL YEARLY COSTS $1,538,129
RECOMMENDED SAVINGS* $602,419 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $6,317 - $6,317
35,097
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,664 - $5,664
31,467
kWh
- - -
03 2.4221: Install compressor air intakes in coolest locations $369 $1,363 $369
2,051
kWh
- - -
04 2.2437: Recover waste heat from equipment $6,680 $1,717 - - $6,680
-
MMBtu
-
05 4.212: Adopt in-house material generation $320,339 $149,572 $(-4,598.0)
(-25,542)
kWh
$(-1,667.0)
-
kW-mo/yr
- $326,604
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,616 $7,758 $2,831
15,725
kWh
$1,785
-
kW-mo/yr
- -
07 2.9114: Use solar heat to make electricty $257,368 $1,284,211 $204,252
1,134,744
kWh
$53,116
-
kW-mo/yr
- -
08 2.7221: Lower temperature during the winter season and vice-versa $1,066 - - - $1,066
-
MMBtu
-
TOTAL RECOMMENDED $602,419 $1,444,621 $214,835
1,193,542
kWh
$53,234
-
kW-mo/yr
$7,746
-
MMBtu
$326,604
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs