Assessment Year | 2011 |
---|---|
Principal Product | Heavy-gauge metal tanks |
NAICS | 332420: Metal Tank (Heavy Gauge) Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $500 k to 1M |
# of Employees | 283 |
Plant Area |
237,088
ft2
|
Annual Production | 170,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $365,720 | 7,902,422 |
kWh
|
$0.046 |
Electricity Demand | $77,902 | 51,850 |
kW-mo/yr
|
$1.50 |
Electricity Fees | $51,250 | - |
|
- |
Natural Gas | $324,242 | 59,322 |
MMBtu
|
$5.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $56,862 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,417 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $8,451 | $55,000 | - | - |
$8,451
-
MMBtu
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $18,396 | $2,000 |
$17,397
266,410
kWh
|
$999
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,514 | $31,299 |
$16,408
354,409
kWh
|
$1,092
-
kW-mo/yr
|
- | $4 | $10 | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,480 | $20 |
$5,958
128,159
kWh
|
$522
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $6,021 | $8,100 |
$5,757
124,349
kWh
|
$264
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $56,862 | $96,419 |
$45,520
873,327
kWh
|
$2,877
-
kW-mo/yr
|
$8,451
-
MMBtu
|
$4 | $10 | ||
TOTAL IMPLEMENTED | $24,417 | $10,100 |
$23,154
390,759
kWh
|
$1,263
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs