ITAC Assessment: TN0231
ITAC logo
ITAC Assessment: TN0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product UNIFORMS
NAICS
n/a
SIC 2325: Men's and Boys' Separate Trousers and Slacks
Sales Range $1
M
to 5
M
# of Employees 200
Plant Area
n/a
Annual Production 526,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,531 528,136
kWh
Natural Gas $48,535 8,271
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,134 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,414

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $7,322 $500 - $7,322
-
MMBtu
-
02 2.2136: Install / repair insulation on steam lines $4,342 $3,285 - $4,342
-
MMBtu
-
03 2.6232: Install set-back timers $1,771 - $1,771
28,722
kWh
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $113 $400 - $513
-
MMBtu
$(-400.0)
05 2.6212: Turn off equipment during breaks, reduce operating time $922 - $922
14,947
kWh
- -
06 2.2136: Install / repair insulation on steam lines $124 $42 - $124
-
MMBtu
-
07 2.2511: Insulate bare equipment $142 $205 - $142
-
MMBtu
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $398 - $398
6,448
kWh
- -
TOTAL RECOMMENDED $15,134 $4,432 $3,091
50,117
kWh
$12,443
-
MMBtu
$(-400.0)
TOTAL IMPLEMENTED $7,414 $3,932 $2,693
43,669
kWh
$5,121
-
MMBtu
$(-400.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs