| Assessment Year | 2001 |
|---|---|
| Principal Product | Sheet Metal |
| NAICS |
n/a
|
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
121,000
ft2
|
| Annual Production | 24,000,000
lb
|
| Production Hrs. Annual | 0
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $50,231 | 1,666,700 |
kWh
|
$0.030 |
| Electricity Demand | $43,698 | 4,438 |
kW-mo/yr
|
$9.85 |
| Electricity Fees | $864 | - |
|
- |
| Natural Gas | $63,472 | 8,155 |
MMBtu
|
$7.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,810 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,040 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,290 | $23,430 |
$6,430
176,100
kWh
|
$4,860
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $6,500 | $21,650 |
$(-160.0)
(-5,400)
kWh
|
$(-70.0)
-
kW-mo/yr
|
$6,730
-
MMBtu
|
- | - | |
| 03 | 2.7221: Lower temperature during the winter season and vice-versa | $4,500 | $6,270 | - | - |
$4,500
-
MMBtu
|
- | - | |
| 04 | 2.3191: Use demand controller or load shedder | $2,960 | $6,500 | - |
$2,960
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,290 | $360 |
$1,770
58,600
kWh
|
$1,300
-
kW-mo/yr
|
- | $(-780.0) | - | |
| 06 | 4.515: Install shelves / racks to utilize unused space | $7,270 | $8,240 | - | - | - | - | $7,270 | |
| TOTAL RECOMMENDED | $34,810 | $66,450 |
$8,040
229,300
kWh
|
$9,050
-
kW-mo/yr
|
$11,230
-
MMBtu
|
$(-780.0) | $7,270 | ||
| TOTAL IMPLEMENTED | $21,040 | $36,560 |
$8,200
234,700
kWh
|
$9,120
-
kW-mo/yr
|
$4,500
-
MMBtu
|
$(-780.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs