ITAC Assessment: CO0493
ITAC logo
ITAC Assessment: CO0493
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Sheet Metal
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 121,000
ft2
Annual Production 24,000,000
lb
Production Hrs. Annual 0
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,231 1,666,700
kWh
Electricity Demand $43,698 4,438
kW-mo/yr
Electricity Fees $864 -
Natural Gas $63,472 8,155
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,810 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,040

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,290 $23,430 $6,430
176,100
kWh
$4,860
-
kW-mo/yr
- - -
02 2.7243: Improve air circulation with destratification fans / other methods $6,500 $21,650 $(-160.0)
(-5,400)
kWh
$(-70.0)
-
kW-mo/yr
$6,730
-
MMBtu
- -
03 2.7221: Lower temperature during the winter season and vice-versa $4,500 $6,270 - - $4,500
-
MMBtu
- -
04 2.3191: Use demand controller or load shedder $2,960 $6,500 - $2,960
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,290 $360 $1,770
58,600
kWh
$1,300
-
kW-mo/yr
- $(-780.0) -
06 4.515: Install shelves / racks to utilize unused space $7,270 $8,240 - - - - $7,270
TOTAL RECOMMENDED $34,810 $66,450 $8,040
229,300
kWh
$9,050
-
kW-mo/yr
$11,230
-
MMBtu
$(-780.0) $7,270
TOTAL IMPLEMENTED $21,040 $36,560 $8,200
234,700
kWh
$9,120
-
kW-mo/yr
$4,500
-
MMBtu
$(-780.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs