| Assessment Year | 2023 |
|---|---|
| Principal Product | Bread, Buns, and Rolls |
| NAICS | 311812: Commercial Bakeries |
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $100 M to 500M |
| # of Employees | 275 |
| Plant Area |
120,000
ft2
|
| Annual Production | 89,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $342,261 | 6,863,832 |
kWh
|
$0.050 | |
| Electricity Demand | $181,065 | 12,457 |
kW-mo/yr
|
$14.54 | |
| Natural Gas | $375,742 | 51,142 |
MMBtu
|
$7.35 | |
| Waste Disposal Costs | |||||
| Water Usage | $26,980 | 6,238 |
Tgal
|
$4.33 | |
| Water Disposal | $26,102 | 6,238 |
Tgal
|
$4.18 | |
| TOTAL YEARLY COSTS | $952,150 | ||||
| RECOMMENDED SAVINGS* | $130,344 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $51,041 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $44,264 | $3,287 |
$44,264
887,040
kWh
|
- | - | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $41,378 | $10,100 |
$41,378
829,216
kWh
|
- | - | - | |
| 03 | 4.214: Purchase appropriately sized material | $18,022 | $87,000 | - | - |
$18,022
-
MMBtu
|
- | |
| 04 | 2.2515: Use optimum thickness insulation | $14,929 | $45,390 | - | - |
$14,929
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,663 | $1,500 |
$6,907
138,408
kWh
|
$2,756
-
kW-mo/yr
|
- | - | |
| 06 | 2.4112: Install soft-start to eliminate nuisance trips | $2,088 | $4,500 |
$647
12,963
kWh
|
- | - | $1,441 | |
| TOTAL RECOMMENDED | $130,344 | $151,777 |
$93,196
1,867,627
kWh
|
$2,756
-
kW-mo/yr
|
$32,951
-
MMBtu
|
$1,441 | ||
| TOTAL IMPLEMENTED | $51,041 | $11,600 |
$48,285
967,624
kWh
|
$2,756
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs