| Assessment Year | 1984 |
|---|---|
| Principal Product | STEEL JOINTS |
| NAICS |
n/a
|
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $5 M to 10M |
| # of Employees | 120 |
| Plant Area |
n/a
|
| Annual Production | 6,000
ton
|
| Production Hrs. Annual | 4,290
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $108,430 | 1,892,145 |
kWh
|
$0.057 |
| LPG | $17,803 | 2,061 |
MMBtu
|
$8.64 |
| Fuel Oil #2 | $9,500 | 1,330 |
MMBtu
|
$7.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,991 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $5,090 | $13,000 |
$(-4,410.0)
(-77,374)
kWh
|
- |
$9,500
-
MMBtu
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,768 | $95 |
$7,768
136,284
kWh
|
- | - | - | |
| 03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,670 | - |
$6,670
116,940
kWh
|
- | - | - | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,236 | $500 |
$1,236
21,688
kWh
|
- | - | - | |
| 05 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $18,012 | $10,000 |
$322
5,569
kWh
|
- | - | $17,690 | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $1,056 | - |
$1,056
18,464
kWh
|
- | - | - | |
| 07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,159 | $3,500 |
$1,854
32,532
kWh
|
$(-695.0)
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $40,991 | $27,095 |
$14,496
254,103
kWh
|
$(-695.0)
-
MMBtu
|
$9,500
-
MMBtu
|
$17,690 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs