ITAC Assessment: SU0488
ITAC logo
ITAC Assessment: SU0488
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Plastic Bottles and Caps
NAICS 326160: Plastics Bottle Manufacturing
SIC 3085: Plastics Bottles
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 112,500
ft2
Annual Production 1,500,000,000
units
Production Hrs. Annual 8,736
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $509,477 13,779,484
kWh
Electricity Demand $274,515 23,436
kW-mo/yr
Electricity Fees $41,799 -
Natural Gas $10,399 2,511
MMBtu
Waste Disposal Costs
Water Usage $18,986 12,851
Tgal
TOTAL YEARLY COSTS $855,176
RECOMMENDED SAVINGS* $10,330 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,216

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7224: Reduce space conditioning during non-working hours $27 - - - $27
-
MMBtu
- -
02 2.8121: Apply for tax-free status for energy purchases $1,216 $264 - - - - $1,216
03 2.7314: Reduce ventilation air $2,109 $941 $943
23,582
kWh
- $1,165
-
MMBtu
- -
04 3.1161: Eliminate/reduce an operation $6,705 $3,690 $(-30.0)
(-750)
kWh
$(-1,264.7)
-
kW-mo/yr
- - $8,000
05 2.7142: Utilize higher efficiency lamps and/or ballasts $273 $652 $178
4,450
kWh
$71
-
kW-mo/yr
- $14 $10
TOTAL RECOMMENDED $10,330 $5,547 $1,091
27,282
kWh
$(-1,193.3)
-
kW-mo/yr
$1,192
-
MMBtu
$14 $9,226
TOTAL IMPLEMENTED $1,216 $264 - - - - $1,216
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs