Assessment Year | 2004 |
---|---|
Principal Product | Commercial and Residential Lawnmowers |
NAICS | 333111: Farm Machinery and Equipment Manufacturing |
SIC | 3523: Farm Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 323 |
Plant Area |
135,000
ft2
|
Annual Production | 23,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $186,864 | 2,394,000 |
kWh
|
$0.078 |
Electricity Demand | $76,905 | 5,908 |
kW-mo/yr
|
$13.02 |
Natural Gas | $201,164 | 28,497 |
MMBtu
|
$7.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,143 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,601 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,139 | - |
$592
7,588
kWh
|
$547
-
kW-mo/yr
|
- | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $9,582 | - | - | - | - | $9,582 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,367 | $366 |
$1,781
22,828
kWh
|
$586
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,129 | $308 |
$647
8,294
kWh
|
$482
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,105 | $960 |
$717
9,198
kWh
|
$169
-
kW-mo/yr
|
- | $1,219 | |
06 | 2.7135: Install occupancy sensors | $1,344 | $1,090 |
$1,344
17,228
kWh
|
- | - | - | |
07 | 3.6122: Install solid waste incinerator for heat | $16,477 | $25,850 |
$(-70.0)
(-893)
kWh
|
$(-91.0)
-
kW-mo/yr
|
$2,238
-
MMBtu
|
$14,400 | |
TOTAL RECOMMENDED | $34,143 | $28,574 |
$5,011
64,243
kWh
|
$1,693
-
kW-mo/yr
|
$2,238
-
MMBtu
|
$25,201 | ||
TOTAL IMPLEMENTED | $5,601 | $1,634 |
$3,145
40,320
kWh
|
$1,237
-
kW-mo/yr
|
- | $1,219 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs