Assessment Year | 2024 |
---|---|
Principal Product | Milk, Yogurt, Ice cream, Butter |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
65,000
ft2
|
Annual Production | 7,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $487,821 | 3,053,524 |
kWh
|
$0.16 |
Electricity Demand | $195,726 | 7,931 |
kW-mo/yr
|
$24.68 |
Electricity Fees | $2,928 | - |
|
- |
Natural Gas | $287,097 | 19,466 |
MMBtu
|
$14.75 |
TOTAL YEARLY COSTS | $973,572 | |||
RECOMMENDED SAVINGS* | $226,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,003 | $100 |
$3,304
20,673
kWh
|
$699
-
kW-mo/yr
|
- | - | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $16,636 | $2,272 |
$8,484
53,089
kWh
|
- |
$8,152
-
MMBtu
|
- | - | |
03 | 2.2113: Repair or replace steam traps | $16,386 | $2,278 | - | - |
$17,686
-
MMBtu
|
$(-1,300.0) | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,117 | $3,083 |
$18,117
113,375
kWh
|
- | - | - | - | |
05 | 2.2123: Insulate feedwater tank | $1,576 | $1,977 | - | - |
$1,576
-
MMBtu
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $466 | $1,170 |
$253
1,581
kWh
|
$191
-
kW-mo/yr
|
- | $30 | $(-8.0) | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $17,789 | $52,101 | - | - |
$17,789
-
MMBtu
|
- | - | |
08 | 2.2414: Use waste heat from hot flue gases to preheat | $4,505 | $22,063 | - | - |
$4,505
-
MMBtu
|
- | - | |
09 | 2.7243: Improve air circulation with destratification fans / other methods | $5,729 | $28,430 |
$5,729
35,854
kWh
|
- | - | - | - | |
10 | 2.9114: Use solar heat to make electricty | $141,513 | $823,750 |
$141,513
885,566
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $226,720 | $937,224 |
$177,400
1,110,138
kWh
|
$890
-
kW-mo/yr
|
$49,708
-
MMBtu
|
$(-1,270.0) | $(-8.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs