Assessment Year | 1983 |
---|---|
Principal Product | SAW BLADES |
NAICS |
n/a
|
SIC | 3425: Saw Blades and Handsaws |
Sales Range | less than $500 k |
# of Employees | 20 |
Plant Area |
n/a
|
Annual Production | 14,350
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $8,746 | 137,456 |
kWh
|
$0.064 |
Natural Gas | $2,197 | 451 |
MMBtu
|
$4.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,562 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7244: Revise smoke cleanup from operations | $657 | $2,772 |
$657
16,413
kWh
|
- | |
02 | 2.7261: Install timers and/or thermostats | $1,146 | $800 | - |
$1,146
-
MMBtu
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $175 | - |
$175
4,396
kWh
|
- | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $730 | $529 | - |
$730
-
MMBtu
|
|
TOTAL RECOMMENDED | $2,708 | $4,101 |
$832
20,809
kWh
|
$1,876
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,562 | $3,301 |
$832
20,809
kWh
|
$730
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs