ITAC Assessment: KS2310
ITAC logo
ITAC Assessment: KS2310
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Nonwoven Fabrics
NAICS 313230: Nonwoven Fabric Mills
SIC 2297: Non-woven Fabrics
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 65,000
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $531,551 6,493,680
kWh
Natural Gas $23,803 4,481
MMBtu
Waste Disposal Costs
Water Usage $3,482 1,142
Tgal
Water Disposal $3,482 1,142
Tgal
TOTAL YEARLY COSTS $562,318
RECOMMENDED SAVINGS* $79,681 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,318

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2515: Use optimum thickness insulation $6,101 $3,005 - $6,101
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,786 $5,960 $6,786
82,759
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,134 $60 $1,134
13,834
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $264 $236 $264
3,221
kWh
- -
05 2.7135: Install occupancy sensors $4,144 $13,970 $2,922
35,640
kWh
- $1,222
06 2.4321: Upgrade obsolete equipment $8,217 $52,431 $8,217
100,217
kWh
- -
07 2.9114: Use solar heat to make electricty $53,035 $420,746 $53,035
646,763
kWh
- -
TOTAL RECOMMENDED $79,681 $496,408 $72,358
882,434
kWh
$6,101
-
MMBtu
$1,222
TOTAL IMPLEMENTED $14,318 $55,436 $8,217
100,217
kWh
$6,101
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs