Assessment Year | 1982 |
---|---|
Principal Product | EQUIPMENT/UTILITY CONSTRUCTION |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,086 | 1,039,859 |
kWh
|
$0.049 |
Natural Gas | $12,167 | 3,449 |
MMBtu
|
$3.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,158 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $1,720 | - |
$1,720
63,306
kWh
|
- | |
02 | 2.7261: Install timers and/or thermostats | $953 | - | - |
$953
-
MMBtu
|
|
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $485 | $700 | - |
$485
-
MMBtu
|
|
TOTAL RECOMMENDED | $3,158 | $700 |
$1,720
63,306
kWh
|
$1,438
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs