Assessment Year | 2002 |
---|---|
Principal Product | Industrial enzymes |
NAICS |
n/a
|
SIC | 2836: Biological Products, Except Diagnostic Substances |
Sales Range | $50 M to 100M |
# of Employees | 92 |
Plant Area |
140,000
ft2
|
Annual Production | 25,794
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,507,014 | 51,888,000 |
kWh
|
$0.029 |
Electricity Demand | $964,614 | 94,764 |
kW-mo/yr
|
$10.18 |
Other Energy | $60,793 | 215,880 |
MMBtu
|
$0.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $159,827 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $143,247 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,657 | $200 |
$2,489
86,741
kWh
|
$1,168
-
kW-mo/yr
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $143,247 | $20 |
$97,498
3,397,128
kWh
|
$45,749
-
kW-mo/yr
|
|
03 | 2.7135: Install occupancy sensors | $416 | $532 |
$416
14,485
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,119 | $5,981 |
$928
32,328
kWh
|
$1,191
-
kW-mo/yr
|
|
05 | 2.7135: Install occupancy sensors | $10,388 | $30,450 |
$10,388
361,959
kWh
|
- | |
TOTAL RECOMMENDED | $159,827 | $37,183 |
$111,719
3,892,641
kWh
|
$48,108
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $143,247 | $20 |
$97,498
3,397,128
kWh
|
$45,749
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs