| Assessment Year | 2004 |
|---|---|
| Principal Product | CNC routers and associated equipment |
| NAICS | 333991: Power-Driven Handtool Manufacturing |
| SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 105 |
| Plant Area |
109,000
ft2
|
| Annual Production | 610
pieces
|
| Production Hrs. Annual | 5,211
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $51,139 | 834,060 |
kWh
|
$0.061 |
| Electricity Demand | $17,778 | 2,396 |
kW-mo/yr
|
$7.42 |
| Electricity Fees | $189 | - |
|
- |
| Natural Gas | $10,836 | 1,249 |
MMBtu
|
$8.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,399 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,059 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,000 | $14,432 |
$5,900
115,870
kWh
|
$3,100
-
kW-mo/yr
|
- | |
| 02 | 3.5316: Contract a wood pallet recycling company | $2,340 | $72 | - | - |
$2,340
-
Tgal
|
|
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,340 | $2,128 |
$2,340
45,930
kWh
|
- | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $1,590 | $43 |
$1,590
31,234
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,504 | $360 |
$990
19,437
kWh
|
$514
-
kW-mo/yr
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $625 | $600 |
$415
8,160
kWh
|
$210
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $17,399 | $17,635 |
$11,235
220,631
kWh
|
$3,824
-
kW-mo/yr
|
$2,340
-
Tgal
|
||
| TOTAL IMPLEMENTED | $6,059 | $3,131 |
$5,335
104,761
kWh
|
$724
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs