ITAC Assessment: TA0074
ITAC logo
ITAC Assessment: TA0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product CNC routers and associated equipment
NAICS 333991: Power-Driven Handtool Manufacturing
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 109,000
ft2
Annual Production 610
pieces
Production Hrs. Annual 5,211
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,139 834,060
kWh
Electricity Demand $17,778 2,396
kW-mo/yr
Electricity Fees $189 -
Natural Gas $10,836 1,249
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,399 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,059

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,000 $14,432 $5,900
115,870
kWh
$3,100
-
kW-mo/yr
-
02 3.5316: Contract a wood pallet recycling company $2,340 $72 - - $2,340
-
Tgal
03 2.7447: Install vinyl strip / high speed / air curtain doors $2,340 $2,128 $2,340
45,930
kWh
- -
04 2.7124: Make a practice of turning off lights when not needed $1,590 $43 $1,590
31,234
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,504 $360 $990
19,437
kWh
$514
-
kW-mo/yr
-
06 2.4221: Install compressor air intakes in coolest locations $625 $600 $415
8,160
kWh
$210
-
kW-mo/yr
-
TOTAL RECOMMENDED $17,399 $17,635 $11,235
220,631
kWh
$3,824
-
kW-mo/yr
$2,340
-
Tgal
TOTAL IMPLEMENTED $6,059 $3,131 $5,335
104,761
kWh
$724
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs