ITAC Assessment: MS0379
ITAC logo
ITAC Assessment: MS0379
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Lumber
NAICS 321999: All Other Miscellaneous Wood Product Manufacturing
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 98
Plant Area 150,000
ft2
Annual Production 25,000
thousand feet
Production Hrs. Annual 2,550
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $269,910 5,478,711
kWh
Electricity Demand $331,476 18,786
kW-mo/yr
Electricity Fees $(-38,518.0) -
Wood $170,987 310,855
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,575 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Wood Savings
01 2.2437: Recover waste heat from equipment $1,001 $3,105 $582
12,129
kWh
$404
-
kW-mo/yr
$15 -
02 3.6123: Burn wood by-products for heat $2,574 $5,626 $2,048
42,677
kWh
$1,416
-
kW-mo/yr
$52 $(-942.0)
-
MMBtu
TOTAL RECOMMENDED $3,575 $8,731 $2,630
54,806
kWh
$1,820
-
kW-mo/yr
$67 $(-942.0)
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs