| Assessment Year | 2026 |
|---|---|
| Principal Product | Boilers |
| NAICS | 332410: Power Boiler and Heat Exchanger Manufacturing |
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $100 M to 500M |
| # of Employees | 250 |
| Plant Area |
174,500
ft2
|
| Annual Production | 1,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $90,413 | 4,260,760 |
kWh
|
$0.021 |
| Electricity Demand | $79,514 | 5,322 |
kW-mo/yr
|
$14.94 |
| Electricity Fees | $23,067 | - |
|
- |
| Natural Gas | $102,796 | 17,940 |
MMBtu
|
$5.73 |
| Other Gas | $6,941 | 1 |
MMBtu
|
$6,940.59 |
| TOTAL YEARLY COSTS | $302,731 | |||
| RECOMMENDED SAVINGS* | $60,468 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $18,087 | - | - | - | - | - | $18,087 | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,976 | - | - |
$3,976
-
kW-mo/yr
|
- | - | - | |
| 03 | 3.1161: Eliminate/reduce an operation | $2,983 | - |
$945
45,000
kWh
|
$3,137
-
kW-mo/yr
|
$(-1,099.8)
-
MMBtu
|
- | - | |
| 04 | 2.6232: Install set-back timers | $532 | - |
$416
19,815
kWh
|
- |
$116
-
MMBtu
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $304 | - |
$304
14,439
kWh
|
- | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $361 | $274 |
$361
5,185
kWh
|
- | - | - | - | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,372 | $3,433 | - | - |
$3,372
-
MMBtu
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,815 | $23,175 |
$2,904
138,277
kWh
|
$661
-
kW-mo/yr
|
- | - | $6,250 | |
| 09 | 2.4322: Use or replace with energy efficient substitutes | $351 | $866 |
$88
4,205
kWh
|
$86
-
kW-mo/yr
|
- | - | $177 | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $200 | $830 |
$200
9,536
kWh
|
- | - | - | - | |
| 11 | 2.7135: Install occupancy sensors | $591 | $2,569 |
$591
28,162
kWh
|
- | - | - | - | |
| 12 | 2.2414: Use waste heat from hot flue gases to preheat | $5,144 | $37,640 | - | - |
$5,144
-
MMBtu
|
- | - | |
| 13 | 2.1321: Replace fossil fuel equipment with electrical equipment | $10,975 | $162,768 |
$(-654.4)
(-31,161)
kWh
|
- | - |
$11,630
-
MMBtu
|
- | |
| 14 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,778 | $21,942 | - | - |
$3,778
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $60,468 | $253,498 |
$5,155
233,457
kWh
|
$7,860
-
kW-mo/yr
|
$11,310
-
MMBtu
|
$11,630
-
MMBtu
|
$24,513 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs