ITAC Assessment: SU0609
ITAC logo
ITAC Assessment: SU0609
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Graphite Tubes/Rods, Ceramic Bearings/Impellers
NAICS 335991: Carbon and Graphite Product Manufacturing
SIC 3624: Carbon and Graphite Products
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 196,000
ft2
Annual Production 400,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,742 8,532,118
kWh
Electricity Demand $248,761 18,031
kW-mo/yr
Electricity Fees $136,531 -
Natural Gas $252,264 49,664
MMBtu
Other Gas $13,512 1
MMBtu
Waste Disposal Costs
Water Usage $26,000 5,206
Tgal
TOTAL YEARLY COSTS $890,811
RECOMMENDED SAVINGS* $67,106 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $10,810 - - - - $10,810
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $23,440 - - $23,440
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $881 - $502
20,083
kWh
$379
-
kW-mo/yr
- -
04 3.1161: Eliminate/reduce an operation $1,099 - $478
19,125
kWh
$1,035
-
kW-mo/yr
$(-414.3)
-
MMBtu
-
05 4.463: Modify facility to avoid excess maintenance costs $1,861 - - - - $1,861
06 2.2511: Insulate bare equipment $476 $299 - - $476
-
MMBtu
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,808 $1,328 $1,030
41,190
kWh
$778
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $176 $286 $70
2,803
kWh
$53
-
kW-mo/yr
- $53
09 2.7444: Close holes and openings in building such as broken windows $3,060 $5,600 - - $3,060
-
MMBtu
-
10 2.4322: Use or replace with energy efficient substitutes $1,118 $2,055 $271
10,848
kWh
$205
-
kW-mo/yr
- $642
11 2.1233: Analyze flue gas for proper air/fuel ratio $734 $1,461 - - $734
-
MMBtu
-
12 2.4221: Install compressor air intakes in coolest locations $991 $2,018 $695
27,797
kWh
$296
-
kW-mo/yr
- -
13 2.7135: Install occupancy sensors $399 $1,351 $399
15,978
kWh
- - -
14 2.7224: Reduce space conditioning during non-working hours $225 $836 $22
880
kWh
$203
-
kW-mo/yr
- -
15 2.2437: Recover waste heat from equipment $6,172 $23,700 - - $6,172
-
MMBtu
-
16 2.2414: Use waste heat from hot flue gases to preheat $13,625 $54,395 - - $13,625
-
MMBtu
-
17 2.6211: Conserve energy by efficient use of vending machines $230 $1,018 $230
9,198
kWh
- - -
TOTAL RECOMMENDED $67,106 $94,346 $3,698
147,903
kWh
$26,389
-
kW-mo/yr
$23,653
-
MMBtu
$13,366
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs