| Assessment Year | 2026 |
|---|---|
| Principal Product | Copper Wire |
| NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
| SIC | 3351: Rolling, Drawing, and Extruding Of Copper |
| Sales Range | $100 M to 500M |
| # of Employees | 202 |
| Plant Area |
326,000
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,042,971 | 16,725,509 |
kWh
|
$0.062 | |
| Electricity Demand | $350,239 | 43,100 |
kW-mo/yr
|
$8.13 | |
| Electricity Fees | $12,338 | - |
|
- | |
| LPG | $199,085 | 13,434 |
MMBtu
|
$14.82 | |
| Waste Disposal Costs | |||||
| Water Usage | $26,953 | 6,174 |
Tgal
|
$4.37 | |
| TOTAL YEARLY COSTS | $1,631,586 | ||||
| RECOMMENDED SAVINGS* | $125,329 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,688 | - |
$1,688
27,225
kWh
|
- | - | - | |
| 02 | 3.1161: Eliminate/reduce an operation | $1,725 | - |
$1,507
24,300
kWh
|
$1,755
-
kW-mo/yr
|
$(-1,536.8)
-
MMBtu
|
- | |
| 03 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $6,197 | $1,433 |
$6,197
99,951
kWh
|
- | - | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $4,677 | $1,188 | - | - |
$4,677
-
MMBtu
|
- | |
| 05 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $10,934 | $3,466 | - | - |
$10,934
-
MMBtu
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $941 | $387 |
$941
15,185
kWh
|
- | - | - | |
| 07 | 2.4322: Use or replace with energy efficient substitutes | $489 | $708 |
$224
3,616
kWh
|
$40
-
kW-mo/yr
|
- | $224 | |
| 08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,057 | $1,985 | - | - |
$1,057
-
MMBtu
|
- | |
| 09 | 2.6211: Conserve energy by efficient use of vending machines | $607 | $1,271 |
$607
9,784
kWh
|
- | - | - | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,294 | $5,655 |
$2,294
36,997
kWh
|
- | - | - | |
| 11 | 2.9114: Use solar heat to make electricty | $2,174 | $5,654 |
$2,174
35,064
kWh
|
- | - | - | |
| 12 | 2.1321: Replace fossil fuel equipment with electrical equipment | $75,844 | $285,000 |
$(-19,889.6)
(-320,800)
kWh
|
- |
$95,734
-
MMBtu
|
- | |
| 13 | 2.4321: Upgrade obsolete equipment | $16,702 | $117,000 |
$16,702
269,391
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $125,329 | $423,748 |
$12,444
200,713
kWh
|
$1,795
-
kW-mo/yr
|
$110,865
-
MMBtu
|
$224 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs