ITAC Assessment: TN0245
ITAC logo
ITAC Assessment: TN0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product PANTS & SHORTS
NAICS
n/a
SIC 2339: Women's, Misses', and Juniors' Outerwear, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 283
Plant Area
n/a
Annual Production 1,032,000
pieces
Production Hrs. Annual 3,772
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,990 1,468,933
kWh
Fuel Oil #2 $51,029 7,280
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,169 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,863

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.2136: Install / repair insulation on steam lines $5,632 $232 $1,452
24,619
kWh
$4,180
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $3,837 - - $4,737
-
MMBtu
$(-900.0)
03 2.7111: Reduce illumination to minimum necessary levels $6,185 - $6,185
104,924
kWh
- -
04 2.1131: Repair faulty insulation in furnaces, boilers, etc $1,176 $400 - $1,176
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,233 $225 $3,233
54,807
kWh
- -
06 2.2135: Repair and eliminate steam leaks $976 $29 $191
3,224
kWh
$785
-
MMBtu
-
07 2.2511: Insulate bare equipment $1,130 $214 $366
6,155
kWh
$764
-
MMBtu
-
TOTAL RECOMMENDED $22,169 $1,100 $11,427
193,729
kWh
$11,642
-
MMBtu
$(-900.0)
TOTAL IMPLEMENTED $19,863 $486 $11,061
187,574
kWh
$9,702
-
MMBtu
$(-900.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs