| Assessment Year | 1985 |
|---|---|
| Principal Product | PANTS & SHORTS |
| NAICS |
n/a
|
| SIC | 2339: Women's, Misses', and Juniors' Outerwear, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 283 |
| Plant Area |
n/a
|
| Annual Production | 1,032,000
pieces
|
| Production Hrs. Annual | 3,772
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,990 | 1,468,933 |
kWh
|
$0.059 |
| Fuel Oil #2 | $51,029 | 7,280 |
MMBtu
|
$7.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,169 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,863 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $5,632 | $232 |
$1,452
24,619
kWh
|
$4,180
-
MMBtu
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,837 | - | - |
$4,737
-
MMBtu
|
$(-900.0) | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $6,185 | - |
$6,185
104,924
kWh
|
- | - | |
| 04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,176 | $400 | - |
$1,176
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,233 | $225 |
$3,233
54,807
kWh
|
- | - | |
| 06 | 2.2135: Repair and eliminate steam leaks | $976 | $29 |
$191
3,224
kWh
|
$785
-
MMBtu
|
- | |
| 07 | 2.2511: Insulate bare equipment | $1,130 | $214 |
$366
6,155
kWh
|
$764
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $22,169 | $1,100 |
$11,427
193,729
kWh
|
$11,642
-
MMBtu
|
$(-900.0) | ||
| TOTAL IMPLEMENTED | $19,863 | $486 |
$11,061
187,574
kWh
|
$9,702
-
MMBtu
|
$(-900.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs