Assessment Year | 2024 |
---|---|
Principal Product | Plumbing Fixtures |
NAICS | 326191: Plastics Plumbing Fixture Manufacturing |
SIC | 3088: Plastics Plumbing Fixtures |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
151,338
ft2
|
Annual Production | 110,000
units
|
Production Hrs. Annual | 2,270
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $129,608 | 1,944,360 |
kWh
|
$0.067 | |
Electricity Demand | $80,271 | 8,909 |
kW-mo/yr
|
$9.01 | |
Electricity Fees | $1,824 | - |
|
- | |
LPG | $436,674 | 20,782 |
MMBtu
|
$21.01 | |
Fuel Oil #1 | $877,473 | 31,050 |
MMBtu
|
$28.26 | |
Waste Disposal Costs | |||||
Water Usage | $8,073 | 907 |
Tgal
|
$8.90 | |
TOTAL YEARLY COSTS | $1,533,923 | ||||
RECOMMENDED SAVINGS* | $137,941 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $87,396 | $642,159 |
$60,083
900,795
kWh
|
$27,313
-
kW-mo/yr
|
- | - | - | |
02 | 2.8223: Add air shields to trucks to increase fuel mileage | $43,888 | $15,124 | - | - |
$43,888
-
MMBtu
|
- | - | |
03 | 4.322: Eliminate old stock and modify inventory control | $4,022 | $1,805 | - | - | - | - | $4,022 | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,282 | $4,696 |
$1,331
19,964
kWh
|
$951
-
kW-mo/yr
|
- | - | - | |
05 | 2.7132: Install timers on light switches in little used areas | $137 | $172 |
$137
2,051
kWh
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $122 | $476 |
$71
1,059
kWh
|
$51
-
kW-mo/yr
|
- | - | - | |
07 | 2.7144: Install spectral reflectors / delamp | $94 | $52 |
$30
445
kWh
|
$22
-
kW-mo/yr
|
- | $42 | - | |
TOTAL RECOMMENDED | $137,941 | $664,484 |
$61,652
924,314
kWh
|
$28,337
-
kW-mo/yr
|
$43,888
-
MMBtu
|
$42 | $4,022 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs