Assessment Year | 2023 |
---|---|
Principal Product | Electronics and electronic components |
NAICS | 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 155 |
Plant Area |
55,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $112,395 | 1,186,210 |
kWh
|
$0.095 | |
Electricity Demand | $43,023 | 3,853 |
kW-mo/yr
|
$11.17 | |
Electricity Fees | $2,089 | - |
|
- | |
Natural Gas | $23,152 | 24,973 |
MMBtu
|
$0.93 | |
Other Gas | $205 | 24,973 |
MMBtu
|
$0.008 | |
Waste Disposal Costs | |||||
Water Usage | $6,479 | 392 |
Tgal
|
$16.52 | |
Solid Waste (non-haz) | $21,539 | 1 |
lb
|
$21,538.90 | |
TOTAL YEARLY COSTS | $208,882 | ||||
RECOMMENDED SAVINGS* | $31,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $21,903 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7122: Disconnect ballasts | $6,186 | - |
$4,575
48,160
kWh
|
$1,611
-
kW-mo/yr
|
- | - | |
02 | 4.821: Pay bills on time to avoid late fees | $1,177 | - | - | - | - | $1,177 | |
03 | 2.4239: Eliminate or reduce compressed air usage | $1,864 | - |
$1,864
19,617
kWh
|
- | - | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $6,803 | - | - | - | - | $6,803 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,119 | $2,000 |
$3,119
32,827
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,953 | $8,568 |
$6,163
64,872
kWh
|
$2,173
-
kW-mo/yr
|
- | $1,617 | |
07 | 2.7135: Install occupancy sensors | $827 | $580 |
$827
8,704
kWh
|
- | - | - | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,165 | - | - |
$1,165
-
kW-mo/yr
|
- | - | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $24 | $100 | - | - |
$24
-
MMBtu
|
- | |
10 | 2.4221: Install compressor air intakes in coolest locations | $728 | - |
$728
7,664
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $31,845 | $11,248 |
$17,275
181,844
kWh
|
$4,949
-
kW-mo/yr
|
$24
-
MMBtu
|
$9,597 | ||
TOTAL IMPLEMENTED | $21,903 | $11,248 |
$10,108
106,403
kWh
|
$2,173
-
kW-mo/yr
|
$24
-
MMBtu
|
$9,597 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs