ITAC Assessment: SU0532
ITAC logo
ITAC Assessment: SU0532
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Electronics and electronic components
NAICS 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 155
Plant Area 55,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $112,395 1,186,210
kWh
Electricity Demand $43,023 3,853
kW-mo/yr
Electricity Fees $2,089 -
Natural Gas $23,152 24,973
MMBtu
Other Gas $205 24,973
MMBtu
Waste Disposal Costs
Water Usage $6,479 392
Tgal
Solid Waste (non-haz) $21,539 1
lb
TOTAL YEARLY COSTS $208,882
RECOMMENDED SAVINGS* $31,845 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,903

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.7122: Disconnect ballasts $6,186 - $4,575
48,160
kWh
$1,611
-
kW-mo/yr
- -
02 4.821: Pay bills on time to avoid late fees $1,177 - - - - $1,177
03 2.4239: Eliminate or reduce compressed air usage $1,864 - $1,864
19,617
kWh
- - -
04 2.8121: Apply for tax-free status for energy purchases $6,803 - - - - $6,803
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,119 $2,000 $3,119
32,827
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $9,953 $8,568 $6,163
64,872
kWh
$2,173
-
kW-mo/yr
- $1,617
07 2.7135: Install occupancy sensors $827 $580 $827
8,704
kWh
- - -
08 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,165 - - $1,165
-
kW-mo/yr
- -
09 2.7447: Install vinyl strip / high speed / air curtain doors $24 $100 - - $24
-
MMBtu
-
10 2.4221: Install compressor air intakes in coolest locations $728 - $728
7,664
kWh
- - -
TOTAL RECOMMENDED $31,845 $11,248 $17,275
181,844
kWh
$4,949
-
kW-mo/yr
$24
-
MMBtu
$9,597
TOTAL IMPLEMENTED $21,903 $11,248 $10,108
106,403
kWh
$2,173
-
kW-mo/yr
$24
-
MMBtu
$9,597
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs