ITAC Assessment: SU0531
ITAC logo
ITAC Assessment: SU0531
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Air Filtration Products and Media
NAICS 333912: Air and Gas Compressor Manufacturing
SIC 3569: General Industrial Machinery and Equipment, Not Elsewhere
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area 155,000
ft2
Annual Production 100,000
units
Production Hrs. Annual 4,290
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,666 1,852,961
kWh
Electricity Demand $66,769 6,214
kW-mo/yr
Electricity Fees $12,584 -
Natural Gas $26,652 15,131
MMBtu
TOTAL YEARLY COSTS $174,672
RECOMMENDED SAVINGS* $59,012 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $6,031 - - - - $6,031
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,557 - - $3,557
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $8,464 - $8,464
228,377
kWh
- - -
04 2.7122: Disconnect ballasts $603 - $336
9,060
kWh
$268
-
kW-mo/yr
- -
05 2.4322: Use or replace with energy efficient substitutes $1,436 $70 $972
26,276
kWh
$790
-
kW-mo/yr
$(-326.5)
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,000 $102 $97
2,621
kWh
$39
-
kW-mo/yr
- $864
07 2.7447: Install vinyl strip / high speed / air curtain doors $1,355 $156 - - $1,355
-
MMBtu
-
08 2.9114: Use solar heat to make electricty $32,789 $29,395 $10,612
286,810
kWh
$22,177
-
kW-mo/yr
- -
09 2.2437: Recover waste heat from equipment $428 $528 - - $428
-
MMBtu
-
10 2.7492: Use proper thickness of insulation on building envelope $1,531 $2,041 - - $1,531
-
MMBtu
-
11 2.4221: Install compressor air intakes in coolest locations $1,818 $8,523 $1,818
49,127
kWh
- - -
TOTAL RECOMMENDED $59,012 $40,815 $22,299
602,271
kWh
$26,831
-
kW-mo/yr
$2,987
-
MMBtu
$6,895
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs