Assessment Year | 2023 |
---|---|
Principal Product | Reinforcement products- drywall tape, glasgrid, gaspave, wall patches |
NAICS | 313230: Nonwoven Fabric Mills |
SIC | 2297: Non-woven Fabrics |
Sales Range | $100 M to 500M |
# of Employees | 220 |
Plant Area |
209,000
ft2
|
Annual Production | 27,065,063
units
|
Production Hrs. Annual | 8,616
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $326,214 | 6,720,651 |
kWh
|
$0.049 |
Electricity Demand | $143,142 | 12,732 |
kW-mo/yr
|
$11.24 |
Electricity Fees | $51,730 | - |
|
- |
Natural Gas | $147,505 | 17,883 |
MMBtu
|
$8.25 |
TOTAL YEARLY COSTS | $668,591 | |||
RECOMMENDED SAVINGS* | $18,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $3,551 | $211 |
$(-12.1)
(-246)
kWh
|
$(-7.2)
-
kW-mo/yr
|
$3,570
-
MMBtu
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,608 | $1,343 |
$2,608
53,222
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $283 | $402 |
$87
1,780
kWh
|
$27
-
kW-mo/yr
|
- | $168 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,441 | $6,444 |
$1,388
28,628
kWh
|
$441
-
kW-mo/yr
|
- | $612 | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,131 | $8,940 | - | - |
$2,131
-
MMBtu
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,193 | $21,150 |
$(-40.4)
(-823)
kWh
|
- |
$3,233
-
MMBtu
|
- | |
07 | 2.9114: Use solar heat to make electricty | $4,126 | $28,596 |
$4,126
84,195
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $18,332 | $67,085 |
$8,157
166,755
kWh
|
$461
-
kW-mo/yr
|
$8,934
-
MMBtu
|
$780 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs