| Assessment Year | 2023 |
|---|---|
| Principal Product | Reinforcement products- drywall tape, glasgrid, gaspave, wall patches |
| NAICS | 313230: Nonwoven Fabric Mills |
| SIC | 2297: Non-woven Fabrics |
| Sales Range | $100 M to 500M |
| # of Employees | 220 |
| Plant Area |
209,000
ft2
|
| Annual Production | 27,065,063
units
|
| Production Hrs. Annual | 8,616
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $326,214 | 6,720,651 |
kWh
|
$0.049 |
| Electricity Demand | $143,142 | 12,732 |
kW-mo/yr
|
$11.24 |
| Electricity Fees | $51,730 | - |
|
- |
| Natural Gas | $147,505 | 17,883 |
MMBtu
|
$8.25 |
| TOTAL YEARLY COSTS | $668,591 | |||
| RECOMMENDED SAVINGS* | $18,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $3,551 | $211 |
$(-12.1)
(-246)
kWh
|
$(-7.2)
-
kW-mo/yr
|
$3,570
-
MMBtu
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,608 | $1,343 |
$2,608
53,222
kWh
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $283 | $402 |
$87
1,780
kWh
|
$27
-
kW-mo/yr
|
- | $168 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,441 | $6,444 |
$1,388
28,628
kWh
|
$441
-
kW-mo/yr
|
- | $612 | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,131 | $8,940 | - | - |
$2,131
-
MMBtu
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,193 | $21,150 |
$(-40.4)
(-823)
kWh
|
- |
$3,233
-
MMBtu
|
- | |
| 07 | 2.9114: Use solar heat to make electricty | $4,126 | $28,596 |
$4,126
84,195
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $18,332 | $67,085 |
$8,157
166,755
kWh
|
$461
-
kW-mo/yr
|
$8,934
-
MMBtu
|
$780 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs