ITAC Assessment: SU0530
ITAC logo
ITAC Assessment: SU0530
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Reinforcement products- drywall tape, glasgrid, gaspave, wall patches
NAICS 313230: Nonwoven Fabric Mills
SIC 2297: Non-woven Fabrics
Sales Range $100
M
to 500
M
# of Employees 220
Plant Area 209,000
ft2
Annual Production 27,065,063
units
Production Hrs. Annual 8,616
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $326,214 6,720,651
kWh
Electricity Demand $143,142 12,732
kW-mo/yr
Electricity Fees $51,730 -
Natural Gas $147,505 17,883
MMBtu
TOTAL YEARLY COSTS $668,591
RECOMMENDED SAVINGS* $18,332 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.7243: Improve air circulation with destratification fans / other methods $3,551 $211 $(-12.1)
(-246)
kWh
$(-7.2)
-
kW-mo/yr
$3,570
-
MMBtu
-
02 2.4221: Install compressor air intakes in coolest locations $2,608 $1,343 $2,608
53,222
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $283 $402 $87
1,780
kWh
$27
-
kW-mo/yr
- $168
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,441 $6,444 $1,388
28,628
kWh
$441
-
kW-mo/yr
- $612
05 2.7447: Install vinyl strip / high speed / air curtain doors $2,131 $8,940 - - $2,131
-
MMBtu
-
06 2.7447: Install vinyl strip / high speed / air curtain doors $3,193 $21,150 $(-40.4)
(-823)
kWh
- $3,233
-
MMBtu
-
07 2.9114: Use solar heat to make electricty $4,126 $28,596 $4,126
84,195
kWh
- - -
TOTAL RECOMMENDED $18,332 $67,085 $8,157
166,755
kWh
$461
-
kW-mo/yr
$8,934
-
MMBtu
$780
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs