ITAC Assessment: OR0209
ITAC logo
ITAC Assessment: OR0209
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Hot Dip Galvanizing
NAICS
n/a
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 20,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,330 820,926
kWh
Natural Gas $100,913 25,900
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $99,391 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $98,659

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $732 $750 $732
15,533
kWh
- -
02 2.1116: Improve combustion control capability $27,860 $12,000 - $27,860
-
MMBtu
-
03 2.7124: Make a practice of turning off lights when not needed $274 - $274
7,034
kWh
- -
04 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $2,640 $2,670 $2,640
67,702
kWh
- -
05 2.4133: Use most efficient type of electric motors $185 $248 $185
4,103
kWh
- -
06 3.1191: Change procedures / equipment / operating conditions $67,700 $260,000 - - $67,700
-
lb
TOTAL RECOMMENDED $99,391 $275,668 $3,831
94,372
kWh
$27,860
-
MMBtu
$67,700
-
lb
TOTAL IMPLEMENTED $98,659 $274,918 $3,099
78,839
kWh
$27,860
-
MMBtu
$67,700
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs