Assessment Year | 2024 |
---|---|
Principal Product | stamped parts for motor vehicles |
NAICS | 336111: Automobile Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $50 M to 100M |
# of Employees | 162 |
Plant Area |
196,000
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $193,660 | 5,201,408 |
kWh
|
$0.037 |
Electricity Demand | $283,460 | 11,140 |
kW-mo/yr
|
$25.45 |
Natural Gas | $80,614 | 10,307 |
MMBtu
|
$7.82 |
TOTAL YEARLY COSTS | $557,734 | |||
RECOMMENDED SAVINGS* | $104,688 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,842 | $16,170 |
$3,842
103,865
kWh
|
- | - | - | |
02 | 2.2622: Replace existing chiller with high efficiency model | $3,668 | $35,570 |
$1,135
30,680
kWh
|
$2,533
-
kW-mo/yr
|
- | - | |
03 | 2.9114: Use solar heat to make electricty | $62,544 | $926,250 |
$48,369
1,307,289
kWh
|
$14,175
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $23,108 | $9,760 | - | - |
$23,108
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $3,599 | $7,900 |
$1,515
40,945
kWh
|
$2,084
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,987 | $1,000 |
$2,721
62,142
kWh
|
$3,266
-
kW-mo/yr
|
- | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,940 | $870 |
$554
14,976
kWh
|
$762
-
kW-mo/yr
|
- | $624 | |
TOTAL RECOMMENDED | $104,688 | $997,520 |
$58,136
1,559,897
kWh
|
$22,820
-
kW-mo/yr
|
$23,108
-
MMBtu
|
$624 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs