ITAC Assessment: SU0515
ITAC logo
ITAC Assessment: SU0515
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Compressed Gas
NAICS 325120: Industrial Gas Manufacturing
SIC 2813: Industrial Gases
Sales Range $50
M
to 100
M
# of Employees 90
Plant Area 130,000
ft2
Annual Production 650,000
units
Production Hrs. Annual 6,260
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,737 706,000
kWh
Electricity Demand $24,226 1,257
kW-mo/yr
Electricity Fees $10,132 -
Natural Gas $24,808 8,497
MMBtu
TOTAL YEARLY COSTS $99,903
RECOMMENDED SAVINGS* $13,530 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,299

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $2,532 $95 - - $2,532 - -
02 2.8121: Apply for tax-free status for energy purchases $531 $95 - - - - $531
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,214 $657 - $1,214
-
kW-mo/yr
- - -
04 3.1161: Eliminate/reduce an operation $1,896 $1,442 $(-75.0)
(-1,287)
kWh
$(-978.0)
-
kW-mo/yr
- - $2,949
05 2.7142: Utilize higher efficiency lamps and/or ballasts $45 $56 $122
2,103
kWh
$56
-
kW-mo/yr
- - $(-133.0)
06 2.6211: Conserve energy by efficient use of vending machines $142 $189 $142
2,442
kWh
- - - -
07 2.7314: Reduce ventilation air $1,768 $2,413 $723
12,473
kWh
- - $1,045
-
MMBtu
-
08 2.4221: Install compressor air intakes in coolest locations $167 $432 $167
2,875
kWh
- - - -
09 2.7447: Install vinyl strip / high speed / air curtain doors $5,236 $23,260 $(-537.1)
(-9,261)
kWh
- - $5,773
-
MMBtu
-
TOTAL RECOMMENDED $13,530 $28,639 $542
9,345
kWh
$292
-
kW-mo/yr
$2,532 $6,818
-
MMBtu
$3,347
TOTAL IMPLEMENTED $8,299 $23,450 $(-537.1)
(-9,261)
kWh
- $2,532 $5,773
-
MMBtu
$531
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs