Assessment Year | 2019 |
---|---|
Principal Product | Lithium Batteries & Rechargeable Battery Packs |
NAICS | 335912: Primary Battery Manufacturing |
SIC | 3692: Primary Batteries, Dry and Wet |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
280,000
ft2
|
Annual Production | 400,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $255,458 | 6,637,706 |
kWh
|
$0.038 | |
Electricity Demand | $109,516 | 15,586 |
kW-mo/yr
|
$7.03 | |
Electricity Fees | $7,599 | - |
|
- | |
Natural Gas | $55,804 | 10,160 |
MMBtu
|
$5.49 | |
Waste Disposal Costs | |||||
Water Usage | $4,549 | 2,030 |
Tgal
|
$2.24 | |
TOTAL YEARLY COSTS | $432,926 | ||||
RECOMMENDED SAVINGS* | $12,874 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $2,721 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7122: Disconnect ballasts | $216 | - |
$148
3,888
kWh
|
$68
-
kW-mo/yr
|
- | - | - | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,702 | $131 | - | - |
$1,702
-
MMBtu
|
- | - | |
03 | 2.7314: Reduce ventilation air | $3,103 | $894 |
$467
12,300
kWh
|
- |
$2,636
-
MMBtu
|
- | - | |
04 | 2.7135: Install occupancy sensors | $803 | $433 |
$803
21,120
kWh
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,955 | $1,607 |
$1,955
51,435
kWh
|
- | - | - | - | |
06 | 3.1161: Eliminate/reduce an operation | $5,095 | $4,500 |
$(-16.0)
(-417)
kWh
|
$(-211.0)
-
kW-mo/yr
|
- | $1,042 | $4,280 | |
TOTAL RECOMMENDED | $12,874 | $7,565 |
$3,357
88,326
kWh
|
$(-143.0)
-
kW-mo/yr
|
$4,338
-
MMBtu
|
$1,042 | $4,280 | ||
TOTAL IMPLEMENTED | $2,721 | $564 |
$951
25,008
kWh
|
$68
-
kW-mo/yr
|
$1,702
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs