Assessment Year | 2017 |
---|---|
Principal Product | Industrial Forging |
NAICS | 332111: Iron and Steel Forging |
SIC | 3462: Iron and Steel Forgings |
Sales Range | $10 M to 50M |
# of Employees | 28 |
Plant Area |
30,000
ft2
|
Annual Production | 3,000,000
units
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,184 | 678,882 |
kWh
|
$0.043 |
Electricity Demand | $44,900 | 3,633 |
kW-mo/yr
|
$12.36 |
Electricity Fees | $3,643 | - |
|
- |
Fuel Oil #2 | $91,263 | 6,893 |
MMBtu
|
$13.24 |
TOTAL YEARLY COSTS | $168,990 | |||
RECOMMENDED SAVINGS* | $29,562 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,037 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,081 | - | - | - |
$1,081
-
MMBtu
|
- | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $527 | $439 | - | - |
$527
-
MMBtu
|
- | - | |
03 | 3.1161: Eliminate/reduce an operation | $1,675 | $1,780 |
$(-58.0)
(-1,350)
kWh
|
$(-445.0)
-
kW-mo/yr
|
- | $1,012 | $1,166 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $145 | $165 |
$53
1,227
kWh
|
$21
-
kW-mo/yr
|
- | $41 | $30 | |
05 | 2.8114: Change rate schedules or other changes in utility service | $25,853 | $72,576 | - | - | - | - | $25,853 | |
06 | 2.4321: Upgrade obsolete equipment | $162 | $556 |
$116
2,716
kWh
|
$46
-
kW-mo/yr
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $119 | $563 |
$119
2,774
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $29,562 | $76,079 |
$230
5,367
kWh
|
$(-378.0)
-
kW-mo/yr
|
$1,608
-
MMBtu
|
$1,053 | $27,049 | ||
TOTAL IMPLEMENTED | $3,037 | $2,899 |
$177
4,140
kWh
|
$(-399.0)
-
kW-mo/yr
|
$1,081
-
MMBtu
|
$1,012 | $1,166 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs