ITAC Assessment: SU0405
ITAC logo
ITAC Assessment: SU0405
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Millwork
NAICS 321918: Other Millwork (including Flooring)
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 30,000
ft2
Annual Production 16,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,921 422,400
kWh
Electricity Demand $17,046 1,725
kW-mo/yr
Electricity Fees $4,615 -
Natural Gas $1,711 299
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,480 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,072

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $1,861 - - - - $1,861
02 2.7224: Reduce space conditioning during non-working hours $609 - - - $609
-
MMBtu
-
03 2.7122: Disconnect ballasts $563 - $318
5,382
kWh
$245
-
kW-mo/yr
- -
04 3.1161: Eliminate/reduce an operation $120 - $97
1,644
kWh
$23
-
kW-mo/yr
- -
05 2.7447: Install vinyl strip / high speed / air curtain doors $337 $83 - - $337
-
MMBtu
-
06 2.6211: Conserve energy by efficient use of vending machines $193 $272 $193
3,274
kWh
- - -
07 2.7314: Reduce ventilation air $513 $822 $199
3,373
kWh
- $314
-
MMBtu
-
08 2.2437: Recover waste heat from equipment $297 $476 - - $297
-
MMBtu
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $168 $336 $103
1,752
kWh
$24
-
kW-mo/yr
- $41
10 3.1161: Eliminate/reduce an operation $607 $1,364 - - - $607
11 2.4221: Install compressor air intakes in coolest locations $212 $637 $212
3,588
kWh
- - -
TOTAL RECOMMENDED $5,480 $3,990 $1,122
19,013
kWh
$292
-
kW-mo/yr
$1,557
-
MMBtu
$2,509
TOTAL IMPLEMENTED $4,072 $2,531 $296
5,026
kWh
$24
-
kW-mo/yr
$1,243
-
MMBtu
$2,509
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs