ITAC Assessment: SU0383
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Heat Exchangers
NAICS 332410: Power Boiler and Heat Exchanger Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $50
M
to 100
M
# of Employees 240
Plant Area 146,865
ft2
Annual Production 77,000,000
units
Production Hrs. Annual 7,488
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $203,967 3,628,109
kWh
Electricity Demand $41,012 10,764
kW-mo/yr
Electricity Fees $15,124 -
Natural Gas $54,762 10,924
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,708 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,177

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $288 - $202
3,600
kWh
$86
-
kW-mo/yr
- - - -
02 2.4314: Use synthetic lubricant $1,074 $200 $923
16,474
kWh
$151
-
kW-mo/yr
- - - -
03 3.1161: Eliminate/reduce an operation $11,567 $5,737 $(-504.0)
(-9,000)
kWh
$(-274.0)
-
kW-mo/yr
- $537 - $11,808
04 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $6,133 $4,684 $6,133
109,516
kWh
- - - - -
05 2.4221: Install compressor air intakes in coolest locations $920 $849 $920
16,427
kWh
- - - - -
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,072 $2,205 $(-245.0)
(-4,374)
kWh
$(-61.0)
-
kW-mo/yr
$1,378
-
MMBtu
- - -
07 2.6211: Conserve energy by efficient use of vending machines $218 $471 $218
3,895
kWh
- - - - -
08 2.7447: Install vinyl strip / high speed / air curtain doors $104 $256 - - $104
-
MMBtu
- - -
09 3.4151: Minimize water usage $3,332 $15,700 - - - - $3,332
-
Tgal
-
TOTAL RECOMMENDED $24,708 $30,102 $7,647
136,538
kWh
$(-98.0)
-
kW-mo/yr
$1,482
-
MMBtu
$537 $3,332
-
Tgal
$11,808
TOTAL IMPLEMENTED $12,177 $6,464 $(-84.0)
(-1,505)
kWh
$(-188.0)
-
kW-mo/yr
$104
-
MMBtu
$537 - $11,808
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs