ITAC Assessment: SU0379
ITAC logo
ITAC Assessment: SU0379
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Bottled and Canned Soft Drinks and Carbonated Waters
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 275,462
ft2
Annual Production 1,995,541
pieces
Production Hrs. Annual 7,255
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $528,133 9,076,426
kWh
Electricity Demand $132,045 23,732
kW-mo/yr
Electricity Fees $310 -
Natural Gas $205,796 34,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,220 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,836 - $1,836
31,540
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,640 $1,169 $12,640
217,187
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $390 $222 $143
2,453
kWh
$19
-
kW-mo/yr
- $228
04 2.7447: Install vinyl strip / high speed / air curtain doors $7,321 $4,766 $(-317.0)
(-5,442)
kWh
$(-100.0)
-
kW-mo/yr
$7,738
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $899 $1,039 $899
15,455
kWh
- - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,134 $14,723 $10,134
174,123
kWh
- - -
TOTAL RECOMMENDED $33,220 $21,919 $25,335
435,316
kWh
$(-81.0)
-
kW-mo/yr
$7,738
-
MMBtu
$228
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs