| Assessment Year | 1997 |
|---|---|
| Principal Product | Dairy Products |
| NAICS |
n/a
|
| SIC | 2026: Fluid Milk |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
24,000
ft2
|
| Annual Production | 104,000,000
lb
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $220,396 | 4,321,219 |
kWh
|
$0.051 |
| Electricity Demand | $38,159 | 7,998 |
kW-mo/yr
|
$4.77 |
| Natural Gas | $59,124 | 12,517 |
MMBtu
|
$4.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $76,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,471 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,485 | $2,869 |
$1,306
25,498
kWh
|
$179
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,376 | $11,050 |
$2,817
55,100
kWh
|
$559
-
kW-mo/yr
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $531 | $531 |
$459
9,086
kWh
|
$72
-
kW-mo/yr
|
- | - | |
| 04 | 2.2514: Cover open tanks | $288 | $63 | - | - |
$288
-
MMBtu
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $287 | $1,000 | - | - |
$287
-
MMBtu
|
- | |
| 06 | 2.1224: Replace boiler | $653 | - | - | - |
$653
-
MMBtu
|
- | |
| 07 | 3.1291: Eliminate practice of mixing waste streams | $4,567 | $2,400 | - | - | - | $4,567 | |
| 08 | 4.441: Install automatic packing equipment | $32,361 | $65,000 |
$(-278.0)
(-5,569)
kWh
|
$(-121.0)
-
kW-mo/yr
|
- | $32,760 | |
| 09 | 4.441: Install automatic packing equipment | $33,242 | $113,600 |
$(-849.0)
(-16,706)
kWh
|
$(-369.0)
-
kW-mo/yr
|
- | $34,460 | |
| TOTAL RECOMMENDED | $76,790 | $196,513 |
$3,455
67,409
kWh
|
$320
-
kW-mo/yr
|
$1,228
-
MMBtu
|
$71,787 | ||
| TOTAL IMPLEMENTED | $1,471 | $1,531 |
$459
9,086
kWh
|
$72
-
kW-mo/yr
|
$940
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs