ITAC Assessment: SU0331
ITAC logo
ITAC Assessment: SU0331
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product HAZMAT Emergency Equipment
NAICS 332710: Machine Shops
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 13
Plant Area 9,500
ft2
Annual Production 3,400
units
Production Hrs. Annual 2,184
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,832 95,645
kWh
Electricity Demand $6,085 534
kW-mo/yr
Electricity Fees $1,377 -
Natural Gas $3,235 373
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,667 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,479

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $808 - - - $808
02 2.8114: Change rate schedules or other changes in utility service $211 - - - $211
03 2.6211: Conserve energy by efficient use of vending machines $19 - $19
307
kWh
- -
04 2.6232: Install set-back timers $299 $228 - $299
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $142 $299 $142
2,320
kWh
- -
06 2.6211: Conserve energy by efficient use of vending machines $188 $384 $188
3,090
kWh
- -
TOTAL RECOMMENDED $1,667 $911 $349
5,717
kWh
$299
-
MMBtu
$1,019
TOTAL IMPLEMENTED $1,479 $527 $161
2,627
kWh
$299
-
MMBtu
$1,019
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs