Assessment Year | 2011 |
---|---|
Principal Product | Liquid Food and Beverage Products |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
255,000
ft2
|
Annual Production | 227,090,784
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $599,171 | 9,675,346 |
kWh
|
$0.062 |
Electricity Demand | $102,568 | 21,555 |
kW-mo/yr
|
$4.76 |
Electricity Fees | $36,977 | - |
|
- |
Natural Gas | $661,729 | 94,173 |
MMBtu
|
$7.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $180,407 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,409 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,700 | - |
$16,700
321,155
kWh
|
- | - | - | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,535 | - |
$2,535
46,384
kWh
|
- | - | - | - | - | - | |
03 | 4.821: Pay bills on time to avoid late fees | $1,460 | - | - | - | $1,460 | - | - | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $911 | - |
$911
17,527
kWh
|
- | - | - | - | - | - | |
05 | 2.4314: Use synthetic lubricant | $256 | - |
$163
3,136
kWh
|
$93
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,350 | $685 |
$6,350
101,120
kWh
|
- | - | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $473 | $115 |
$305
5,869
kWh
|
$93
-
kW-mo/yr
|
- | - | $75 | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $2,218 | $1,072 |
$2,218
38,430
kWh
|
- | - | - | - | - | - | |
09 | 2.7314: Reduce ventilation air | $9,055 | $10,481 |
$677
10,788
kWh
|
$125
-
kW-mo/yr
|
- |
$8,253
-
MMBtu
|
- | - | - | |
10 | 2.7122: Disconnect ballasts | $1,569 | $3,650 |
$756
14,545
kWh
|
$463
-
kW-mo/yr
|
- | - | $350 | - | - | |
11 | 2.6211: Conserve energy by efficient use of vending machines | $477 | $1,172 |
$477
8,143
kWh
|
- | - | - | - | - | - | |
12 | 3.1161: Eliminate/reduce an operation | $3,421 | $12,720 | - | - | - | - | - | $3,421 | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,367 | $12,355 |
$2,142
41,184
kWh
|
$1,225
-
kW-mo/yr
|
- | - | - | - | - | |
14 | 2.2414: Use waste heat from hot flue gases to preheat | $6,727 | $38,955 | - | - | - |
$6,727
-
MMBtu
|
- | - | - | |
15 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $61,110 | $1,000,000 | - | - | - | - | - | - | $61,110 | |
16 | 2.9121: Install wind powered electric generator | $14,224 | $153,902 |
$7,447
87,098
kWh
|
$6,777
-
kW-mo/yr
|
- | - | - | - | - | |
17 | 2.9114: Use solar heat to make electricty | $49,554 | $1,230,647 |
$21,981
308,279
kWh
|
$27,573
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $180,407 | $2,465,754 |
$62,662
1,003,658
kWh
|
$36,349
-
kW-mo/yr
|
$1,460 |
$14,980
-
MMBtu
|
$425 | $3,421 | $61,110 | ||
TOTAL IMPLEMENTED | $39,409 | $64,830 |
$26,408
486,855
kWh
|
$1,318
-
kW-mo/yr
|
$1,460 |
$6,727
-
MMBtu
|
$75 | $3,421 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs