Assessment Year | 2022 |
---|---|
Principal Product | Airplane frames and parts |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 400 |
Plant Area |
403,000
ft2
|
Annual Production | 30
units
|
Production Hrs. Annual | 8,424
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $680,744 | 18,805,839 |
kWh
|
$0.036 |
Electricity Demand | $924,482 | 52,025 |
kW-mo/yr
|
$17.77 |
Electricity Fees | $152,656 | - |
|
- |
Natural Gas | $292,781 | 59,612 |
MMBtu
|
$4.91 |
TOTAL YEARLY COSTS | $2,050,663 | |||
RECOMMENDED SAVINGS* | $111,286 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,227 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $39,902 | $83,130 | - | - |
$39,902
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $37,721 | $113,682 |
$22,198
613,216
kWh
|
$15,523
-
kW-mo/yr
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $25,369 | $20,108 | - | - |
$25,369
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,610 | $23,208 |
$3,087
85,281
kWh
|
$2,523
-
kW-mo/yr
|
- | |
05 | 2.7272: Install heat pipes / raise cooling setpoint | $1,788 | $2,208 |
$1,434
39,607
kWh
|
$354
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $896 | $1,796 |
$535
14,866
kWh
|
$361
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $111,286 | $244,132 |
$27,254
752,970
kWh
|
$18,761
-
kW-mo/yr
|
$65,271
-
MMBtu
|
||
TOTAL IMPLEMENTED | $44,227 | $138,686 |
$25,820
713,363
kWh
|
$18,407
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs