ITAC Assessment: SU0234
ITAC logo
ITAC Assessment: SU0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Manufacturing metals products
NAICS 332721: Precision Turned Product Manufacturing
SIC 3451: Screw Machine Products
Sales Range $50
M
to 100
M
# of Employees 291
Plant Area 280,000
ft2
Annual Production 150,000,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $840,487 11,874,000
kWh
Electricity Demand $75,894 25,308
kW-mo/yr
Electricity Fees $28,300 -
Natural Gas $480,585 40,646
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $162,327 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $152,860

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,432 - $3,958
55,748
kWh
$474
-
kW-mo/yr
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $886 - $817
11,506
kWh
$69
-
kW-mo/yr
- - -
03 2.4314: Use synthetic lubricant $118 - $109
1,530
kWh
$9
-
kW-mo/yr
- - -
04 2.7314: Reduce ventilation air $54,755 $2,502 $11,019
155,203
kWh
$912
-
kW-mo/yr
$42,824
-
MMBtu
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,897 $3,680 $16,529
232,805
kWh
$1,368
-
kW-mo/yr
- - -
06 2.4221: Install compressor air intakes in coolest locations $4,746 $1,114 $4,200
59,162
kWh
$546
-
kW-mo/yr
- - -
07 2.2113: Repair or replace steam traps $2,258 $623 - - $2,258
-
MMBtu
- -
08 2.2414: Use waste heat from hot flue gases to preheat $22,470 $8,599 - - $22,470
-
MMBtu
- -
09 2.6231: Utilize controls to operate equipment only when needed $1,901 - $1,901
26,775
kWh
- - - -
10 2.2136: Install / repair insulation on steam lines $7,801 $6,762 - - $7,801
-
MMBtu
- -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $41,955 $48,745 $38,746
545,721
kWh
$3,209
-
kW-mo/yr
- - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $966 $1,217 $371
5,221
kWh
$21
-
kW-mo/yr
- $336 $238
13 2.2511: Insulate bare equipment $792 $1,409 - - $792
-
MMBtu
- -
14 2.2511: Insulate bare equipment $579 $1,245 $(-124.0)
(-1,750)
kWh
$(-6.0)
-
kW-mo/yr
$709
-
MMBtu
- -
15 2.6211: Conserve energy by efficient use of vending machines $271 $708 $271
3,811
kWh
- - - -
16 2.7135: Install occupancy sensors $500 $1,351 $500
7,038
kWh
- - - -
TOTAL RECOMMENDED $162,327 $77,955 $78,297
1,102,770
kWh
$6,602
-
kW-mo/yr
$76,854
-
MMBtu
$336 $238
TOTAL IMPLEMENTED $152,860 $73,671 $70,752
996,515
kWh
$5,963
-
kW-mo/yr
$76,145
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs