Assessment Year | 2006 |
---|---|
Principal Product | Electronic Assembly Equipment |
NAICS | 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 411 |
Plant Area |
248,000
ft2
|
Annual Production | 3,744
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $358,097 | 8,078,400 |
kWh
|
$0.044 |
Electricity Demand | $132,675 | 17,171 |
kW-mo/yr
|
$7.73 |
Electricity Fees | $1,147 | - |
|
- |
Natural Gas | $197,189 | 17,947 |
MMBtu
|
$10.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,085 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,708 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,030 | - |
$2,165
49,205
kWh
|
$865
-
kW-mo/yr
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,876 | - |
$2,166
49,218
kWh
|
$710
-
kW-mo/yr
|
- | - | |
03 | 3.1191: Change procedures / equipment / operating conditions | $1,612 | - |
$1,233
28,022
kWh
|
$379
-
kW-mo/yr
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $890 | - |
$666
15,136
kWh
|
$224
-
kW-mo/yr
|
- | - | |
05 | 4.821: Pay bills on time to avoid late fees | $773 | - | - | - | $773 | - | |
06 | 2.2511: Insulate bare equipment | $1,165 | $225 | - | - | - |
$1,165
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,647 | $583 |
$1,230
27,955
kWh
|
$417
-
kW-mo/yr
|
- | - | |
08 | 2.1232: Keep boiler tubes clean | $2,880 | $1,534 | - | - | - |
$2,880
-
MMBtu
|
|
09 | 2.4221: Install compressor air intakes in coolest locations | $1,307 | $1,182 |
$936
21,253
kWh
|
$371
-
kW-mo/yr
|
- | - | |
10 | 2.6231: Utilize controls to operate equipment only when needed | $8,585 | $9,380 |
$8,585
195,104
kWh
|
- | - | - | |
11 | 2.7314: Reduce ventilation air | $12,512 | $26,994 |
$12,249
278,379
kWh
|
$263
-
kW-mo/yr
|
- | - | |
12 | 2.2414: Use waste heat from hot flue gases to preheat | $4,616 | $11,554 | - | - | - |
$4,616
-
MMBtu
|
|
13 | 2.6211: Conserve energy by efficient use of vending machines | $517 | $1,545 |
$416
9,461
kWh
|
$101
-
kW-mo/yr
|
- | - | |
14 | 2.7135: Install occupancy sensors | $651 | $2,039 |
$543
12,361
kWh
|
$108
-
kW-mo/yr
|
- | - | |
15 | 2.3212: Optimize plant power factor | $1,024 | $9,635 | - | - | $1,024 | - | |
TOTAL RECOMMENDED | $44,085 | $64,671 |
$30,189
686,094
kWh
|
$3,438
-
kW-mo/yr
|
$1,797 |
$8,661
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,708 | $2,117 |
$7,460
169,536
kWh
|
$2,595
-
kW-mo/yr
|
$773 |
$2,880
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs