ITAC Assessment: SU0232
ITAC logo
ITAC Assessment: SU0232
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Electronic Assembly Equipment
NAICS 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 411
Plant Area 248,000
ft2
Annual Production 3,744
pieces
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $358,097 8,078,400
kWh
Electricity Demand $132,675 17,171
kW-mo/yr
Electricity Fees $1,147 -
Natural Gas $197,189 17,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,085 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,708

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $3,030 - $2,165
49,205
kWh
$865
-
kW-mo/yr
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,876 - $2,166
49,218
kWh
$710
-
kW-mo/yr
- -
03 3.1191: Change procedures / equipment / operating conditions $1,612 - $1,233
28,022
kWh
$379
-
kW-mo/yr
- -
04 2.4314: Use synthetic lubricant $890 - $666
15,136
kWh
$224
-
kW-mo/yr
- -
05 4.821: Pay bills on time to avoid late fees $773 - - - $773 -
06 2.2511: Insulate bare equipment $1,165 $225 - - - $1,165
-
MMBtu
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,647 $583 $1,230
27,955
kWh
$417
-
kW-mo/yr
- -
08 2.1232: Keep boiler tubes clean $2,880 $1,534 - - - $2,880
-
MMBtu
09 2.4221: Install compressor air intakes in coolest locations $1,307 $1,182 $936
21,253
kWh
$371
-
kW-mo/yr
- -
10 2.6231: Utilize controls to operate equipment only when needed $8,585 $9,380 $8,585
195,104
kWh
- - -
11 2.7314: Reduce ventilation air $12,512 $26,994 $12,249
278,379
kWh
$263
-
kW-mo/yr
- -
12 2.2414: Use waste heat from hot flue gases to preheat $4,616 $11,554 - - - $4,616
-
MMBtu
13 2.6211: Conserve energy by efficient use of vending machines $517 $1,545 $416
9,461
kWh
$101
-
kW-mo/yr
- -
14 2.7135: Install occupancy sensors $651 $2,039 $543
12,361
kWh
$108
-
kW-mo/yr
- -
15 2.3212: Optimize plant power factor $1,024 $9,635 - - $1,024 -
TOTAL RECOMMENDED $44,085 $64,671 $30,189
686,094
kWh
$3,438
-
kW-mo/yr
$1,797 $8,661
-
MMBtu
TOTAL IMPLEMENTED $13,708 $2,117 $7,460
169,536
kWh
$2,595
-
kW-mo/yr
$773 $2,880
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs