| Assessment Year | 2020 |
|---|---|
| Principal Product | pressure sensitive labels, functional cartridge bags |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 160 |
| Plant Area |
223,000
ft2
|
| Annual Production | 50,000,000
pieces
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,078,202 | 13,316,288 |
kWh
|
$0.081 | |
| Electricity Demand | $290,697 | 32,987 |
kW-mo/yr
|
$8.81 | |
| Electricity Fees | $2,394 | - |
|
- | |
| Natural Gas | $638,252 | 86,585 |
MMBtu
|
$7.37 | |
| Waste Disposal Costs | |||||
| Water Usage | $12,480 | 431 |
Tgal
|
$28.97 | |
| TOTAL YEARLY COSTS | $2,022,025 | ||||
| RECOMMENDED SAVINGS* | $72,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $59,045 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $41,598 | $51,573 |
$33,800
418,839
kWh
|
$7,797
-
kW-mo/yr
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,133 | $4,500 |
$12,917
159,471
kWh
|
$216
-
kW-mo/yr
|
|
| 03 | 4.454: Modify startup/shutdown times | $7,541 | $1,000 |
$7,541
93,101
kWh
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,769 | $12,768 |
$4,686
57,852
kWh
|
$1,083
-
kW-mo/yr
|
|
| 05 | 2.7224: Reduce space conditioning during non-working hours | $4,314 | $3,400 |
$4,314
53,265
kWh
|
- | |
| TOTAL RECOMMENDED | $72,354 | $73,241 |
$63,259
782,528
kWh
|
$9,096
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $59,045 | $59,473 |
$51,031
631,575
kWh
|
$8,013
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs