ITAC Assessment: CL2006
ITAC logo
ITAC Assessment: CL2006
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product pressure sensitive labels, functional cartridge bags
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 160
Plant Area 223,000
ft2
Annual Production 50,000,000
pieces
Production Hrs. Annual 6,500
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,078,202 13,316,288
kWh
Electricity Demand $290,697 32,987
kW-mo/yr
Electricity Fees $2,394 -
Natural Gas $638,252 86,585
MMBtu
Waste Disposal Costs
Water Usage $12,480 431
Tgal
TOTAL YEARLY COSTS $2,022,025
RECOMMENDED SAVINGS* $72,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,045

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $41,598 $51,573 $33,800
418,839
kWh
$7,797
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $13,133 $4,500 $12,917
159,471
kWh
$216
-
kW-mo/yr
03 4.454: Modify startup/shutdown times $7,541 $1,000 $7,541
93,101
kWh
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,769 $12,768 $4,686
57,852
kWh
$1,083
-
kW-mo/yr
05 2.7224: Reduce space conditioning during non-working hours $4,314 $3,400 $4,314
53,265
kWh
-
TOTAL RECOMMENDED $72,354 $73,241 $63,259
782,528
kWh
$9,096
-
kW-mo/yr
TOTAL IMPLEMENTED $59,045 $59,473 $51,031
631,575
kWh
$8,013
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs