| Assessment Year | 2003 |
|---|---|
| Principal Product | Ductile Iron |
| NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $5 M to 10M |
| # of Employees | 74 |
| Plant Area |
110,000
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $115,315 | 1,921,920 |
kWh
|
$0.060 |
| Electricity Demand | $14,729 | 4,294 |
kW-mo/yr
|
$3.43 |
| Natural Gas | $44,718 | 554 |
MMBtu
|
$80.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $92,923 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $92,923 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,108 | - |
$3,673
61,219
kWh
|
$435
-
kW-mo/yr
|
- | - | |
| 02 | 4.514: Re-arrange equipment layout to reduce handling costs | $58,500 | $16,260 | - | - | - | $58,500 | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $85 | $45 |
$64
1,060
kWh
|
$21
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,102 | $13,384 |
$12,703
211,723
kWh
|
$1,399
-
kW-mo/yr
|
- | - | |
| 05 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $13,639 | $14,240 | - | - |
$13,639
-
MMBtu
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,489 | $10,360 | - | - |
$2,489
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $92,923 | $54,289 |
$16,440
274,002
kWh
|
$1,855
-
kW-mo/yr
|
$16,128
-
MMBtu
|
$58,500 | ||
| TOTAL IMPLEMENTED | $92,923 | $54,289 |
$16,440
274,002
kWh
|
$1,855
-
kW-mo/yr
|
$16,128
-
MMBtu
|
$58,500 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs