| Assessment Year | 2015 |
|---|---|
| Principal Product | Clinical Laboratory Products |
| NAICS | 333249: Other Industrial Machinery Manufacturing |
| SIC | 3821: Laboratory Apparatus and Furniture |
| Sales Range | $100 M to 500M |
| # of Employees | 500 |
| Plant Area |
300,000
ft2
|
| Annual Production | 85,000,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $165,866 | 3,788,419 |
kWh
|
$0.044 |
| Electricity Demand | $112,484 | 8,187 |
kW-mo/yr
|
$13.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $126,466 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,783 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $49,400 | $1,400 | - | - | $49,400 | - | |
| 02 | 2.7425: Clean or color roof to reduce solar load | $32,947 | $40,065 |
$17,944
398,750
kWh
|
$15,003
-
kW-mo/yr
|
- | - | |
| 03 | 3.4151: Minimize water usage | $15,193 | $16,600 | - | - | - |
$15,193
-
Tgal
|
|
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $9,862 | $3,960 |
$5,905
131,228
kWh
|
$3,957
-
kW-mo/yr
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,939 | $1,660 |
$2,054
45,639
kWh
|
$2,885
-
kW-mo/yr
|
- | - | |
| 06 | 2.1332: Convert combustion equipment to burn natural gas | $4,265 | $11,000 | - | - | $4,265 | - | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,527 | $6,000 |
$1,466
32,583
kWh
|
$2,061
-
kW-mo/yr
|
- | - | |
| 08 | 2.7134: Use photocell controls | $2,361 | $1,080 |
$1,413
31,394
kWh
|
$948
-
kW-mo/yr
|
- | - | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,647 | $80 |
$685
15,213
kWh
|
$962
-
kW-mo/yr
|
- | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,369 | $4,590 |
$1,369
30,414
kWh
|
- | - | - | |
| 11 | 2.7135: Install occupancy sensors | $956 | $373 |
$571
12,686
kWh
|
$385
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $126,466 | $86,808 |
$31,407
697,907
kWh
|
$26,201
-
kW-mo/yr
|
$53,665 |
$15,193
-
Tgal
|
||
| TOTAL IMPLEMENTED | $21,783 | $32,563 |
$1,940
43,100
kWh
|
$385
-
kW-mo/yr
|
$4,265 |
$15,193
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs