Assessment Year | 2002 |
---|---|
Principal Product | Machine Tools |
NAICS |
n/a
|
SIC | 3541: Machine Tools, Metal Cutting Types |
Sales Range | $100 M to 500M |
# of Employees | 435 |
Plant Area |
534,634
ft2
|
Annual Production | 350
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $709,918 | 15,228,000 |
kWh
|
$0.047 |
Electricity Demand | $408,038 | 32,751 |
kW-mo/yr
|
$12.46 |
Natural Gas | $381,401 | 131,512 |
MMBtu
|
$2.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,006 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $789 | $460 |
$789
11,268
kWh
|
- | - | |
02 | 2.7444: Close holes and openings in building such as broken windows | $23,005 | $17,424 | - | - |
$23,005
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,960 | $480 |
$8,960
127,996
kWh
|
- | - | |
04 | 2.3212: Optimize plant power factor | $9,179 | $7,500 | - | $9,179 | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $15,795 | $7,800 | - | - |
$15,795
-
MMBtu
|
|
06 | 2.4224: Upgrade controls on compressors | $37,278 | $50,000 |
$37,278
532,548
kWh
|
- | - | |
TOTAL RECOMMENDED | $95,006 | $83,664 |
$47,027
671,812
kWh
|
$9,179 |
$38,800
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,749 | $940 |
$9,749
139,264
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs