ITAC Assessment: SU0135
ITAC logo
ITAC Assessment: SU0135
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Machine Tools
NAICS
n/a
SIC 3541: Machine Tools, Metal Cutting Types
Sales Range $100
M
to 500
M
# of Employees 435
Plant Area 534,634
ft2
Annual Production 350
units
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $709,918 15,228,000
kWh
Electricity Demand $408,038 32,751
kW-mo/yr
Natural Gas $381,401 131,512
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $95,006 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,749

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7124: Make a practice of turning off lights when not needed $789 $460 $789
11,268
kWh
- -
02 2.7444: Close holes and openings in building such as broken windows $23,005 $17,424 - - $23,005
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,960 $480 $8,960
127,996
kWh
- -
04 2.3212: Optimize plant power factor $9,179 $7,500 - $9,179 -
05 2.7243: Improve air circulation with destratification fans / other methods $15,795 $7,800 - - $15,795
-
MMBtu
06 2.4224: Upgrade controls on compressors $37,278 $50,000 $37,278
532,548
kWh
- -
TOTAL RECOMMENDED $95,006 $83,664 $47,027
671,812
kWh
$9,179 $38,800
-
MMBtu
TOTAL IMPLEMENTED $9,749 $940 $9,749
139,264
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs