| Assessment Year | 2011 |
|---|---|
| Principal Product | paper |
| NAICS | 322110: Pulp Mills |
| SIC | 2611: Pulp Mills |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
500,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $8,699,045 | 386,919,926 |
kWh
|
$0.022 |
| Natural Gas | $800,000 | 1,000,000 |
MMBtu
|
$0.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $314,567 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1116: Improve combustion control capability | $308,364 | $40,543 | - | - |
$308,364
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,203 | $2,440 |
$5,000
226,933
kWh
|
$1,203
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $314,567 | $42,983 |
$5,000
226,933
kWh
|
$1,203
-
kW-mo/yr
|
$308,364
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs